|
Jun 29
2009
|
One of the smaller engineering challenges the PIPE team have had to overcome is one of keeping the noise level safe in the Transmission Room whilst providing the correct levels of cooling. The room is a concrete box with 150kw of cooling provided by 3 Citec 50kw units. To further add to the complexity, the room doesn't have any raised floor, meaning the units push the cold air out of the top, rather than the bottom. Because everything is tightly spaced, the 'day n' designed air conditioning needed to be installed 'day 1'.
When the units were commissioned, they were noise tested and found to be just inside the safe working limits and too loud for a telephone conversation. To solve this, the PIPE team engaged a local specialist to build a set of baffles to turn the air through 90 degrees as well as split it. The solution has worked a treat and you are now able to safely work in the room without ear protection AND hold a conversation on the inter-station telephone system!





